Alliance Engineering |
El Paso Field Services |
Mid America Resources |
Alpine Energy Corporation
Tim Washington
Project Management, Facility design and onsite inspection of the installation of Well Site Production Facilities in Lafitte, La.
Amec Engineering
Mel Wood
Provided visual inspection services and onsite supervision for the Caesar, Cleopatra & Mardi Gras Projects
Bob Callweld
Provided the onsite supervision for the spooling of 20 miles of 6” XXH pipe line for Petrobras in Carlyss La.
Amoco Production Company
Jim Malboeuf
Onsite Facilities Inspection of numerous project and facilities.
Apache Corporation
Carl Heinrich
Construction Management and Onsite Inspection of the refurbishment of SP62A, SP62B, SP62C, SP62D, MP310A, MP310JA, MP312JA, MP290A, MP289B and MP289C for Hurricane Ivan damaged Production Facilities.
Charlie Jacobs
Construction Management and Onsite Inspection of the refurbishment of VR270, EI306A, EI306B, SP75A, SP52A, SS207A, SS274A, ST139A, VR184A, WD40A, WD75D, BR133A and numerous other platforms for Hurricane Katrina & Rita damaged Production Facilities.
Charlie Jacobs
Construction Management and Onsite Inspection for the caisson repairs for over 50 production caisson damaged due to Hurricanes Katrina & Rita.
Mike Barre
Construction Management and Onsite Inspection for the caisson repairs on EI-224-A & SS-182-B for caissons damaged due to Hurricane Rita.
Fred Schaider
Construction Management and Onsite Inspection of the refurbishment of numerous platforms for damaged by Hurricanes Katrina & Rita.
Norman Porche
Construction Management and Onsite Inspection of the Maintenance repairs and upgrades on SS-207-A, SS-274-A & SS-274-C
Mike Cronk
Construction Management and Onsite Inspection of the refurbishment of numerous platforms for damaged by Hurricanes Katrina & Rita.
Mark Brookman
Construction Management and Onsite Inspection of the refurbishment of numerous platforms for damaged by Hurricanes Katrina & Rita.
British Gas - Trinidad
Stuart Wood
Provided onsite supervising and inspection services for the E&I work on the Dolphin Facility.
Kevin Bourgeois
Provided onsite project management supervision and inspection services for the fabrication of living quarters stacking frame and heliport on the Dolphin Facility.
British Gas - Tunisia
Mike Hunt
Construction Management and Onsite Structural, E&I, Facilities & Pipeline inspection of the $600 Million Miskar Facilities in Tunisia.
Chevron - Cabinda
Provided Visual inspection services over seeing the fabrication of several production skids and instrumentation skids for the Cabinda project.
Chevron - Nigeria
Philip Wallace
Project Management for Cost estimates for EPS Production Barges and Water Injection Barges fro Chevron-Nigeria. Wrote AFE’s and Project Schedules. Perform Preliminary Engineering Study.
Coastal Oil & Gas
Josh Billings
Worked as the construction Superintendent in Coastal Office over the Western Gulf of Mexico.
Kevin Bourgeois
Supervised facilities installation WC 498-B and HI 263 platform onshore and offshore. Inspected the fabrication of the ASME code vessels and production skids for MP 223, WC 498-C, MP 198, and MP 250.
COMM Engineering
John Cuccia
Provided onsite personnel in 43 plants for the gathering of information and the documentation of devices spelled out in the new regulations of 40 CFR 60 pertaining to Greenhouse Gases
Crosstex Energy
Providing the onsite monitoring and governmental reporting for the 40 CFR 60 requirements for V.O.C. Gases. This work is ongoing in multiple plants in South Louisiana
CTC Consulting
Russell Heim
Provided onsite supervision for the onshore hook up of a production facility. Provided onsite supervision for a platform structural study.
Duke Energy
Providing the onsite monitoring and governmental reporting for the 40 CFR 60 requirements for V.O.C. Gases. This work was done in multiple plants in South Louisiana.
Dwyer Petroleum Ventures
Robert Dwyer
Project Management for P&A Wells, Site Clearance and area restoration study – Jefferson Parish. Put together cost estimates and project schedules.
El Paso Production
Josh Billings
Supervised the facilities and structural revisions for WC 515-A.
Bob Bright
Supervised and inspected the installation of VK 285 H2S compressor and facilities upgrade
Mel Woods
Supervised the fabrication and installation of EC 192-C. Supervised the installation of ST 291 compressor and facilities upgrade. Inspected jacket and deck installation for MP 225-D. Installed 4” pipeline for MP 225-D.
Richard Calhoun
Supervised the installation of a Flash Gas Recovery System and the El Paso Plant, Patterson, La.
El Paso – Brazil
Stan Evans
Provided consult for drilling operations
El Paso Field Services
Providing the onsite monitoring and governmental reporting for the 40 CFR 60 requirements for V.O.C. Gases. This work was done in multiple plants in South Louisiana.
Energy XXI
Ricky Giroir
Installed Armor Plate pipe repair system an oil line at MP-73-A
Enervest Operating
Harvey Barney
Performed field assessments and made recommendations for the optimization of the gas compression facilities in the Garden Island Field. Performed post fire assessments in the Garden Island Field.
Buck Wells
Project Management for Gas Compression Plant Optimization Study – Bateman Lake Plant, Prepared Recommendations and wrote AFE’s
ERT
Ray Dickey
Provided the onsite supervision for the installation of the jacket replacement members that broken of during Hurricane Rita.
Exxon / Mobil
Jules Abadie
Provided the construction management and onsite supervision for the fabrication and installation of the production equipment on EI-119-K
General Atlantic
Provided project management services for the removal, refurbishment and installation for the jacket and the decks for EI-245, EI-243, HI-93 and ST-277 facilities.
Global Natural
Provided the project management, supervision and inspection for the refurbishment of the deck and jacket for HI-93-L. Supervised the installation and hookup of the 6” pipeline.
Goldking Energy
Hal Bettis
Provided project management and onsite supervision for the retrieval and re-floating of compressor barge that were pushed on the land by Hurricane Katrina
Great Western Oil & Gas
Provided onsite supervision and inspection services for the installation of 6 flowlines and instrumentation on 3 platforms, EC-282, EC-283 and EC-300.
Provided onsite supervision and inspection services for the fabrication and installation of well access decks on EC-282 and EC-283 facilities.
Provided onsite supervision and inspection services for the refurbishment and installation of SMI-18. Fabricated and installed conductor guides, two 8” risers, boat landing and barge bumpers on SMI-18.
Gulf Island Fabricators
Joe Franklin
Provided Visual inspection services over seeing the fabrication of several production skids and instrumentation skids for the Cabinda project.
Hilcorp Energy Corp.
Jim Bardweld
Provided onsite supervision for the installation of a heliport for Hilcorp’s Lac Blanc Field in White Lake.
Bud Newton
Project Management for Structural Study on three Concrete Barges – Caillou Island Field
Project Management for piping modifications on Lake Barre Central Facility – Put together AFE’s, performed piping design and drafting, put together Bid Packages and installation procedures. Supplied onsite supervision for pre-fabrication and installation.
Project Management for piping modifications dock repairs and barge offloading facilities on Tank Battery #8 – Put together AFE’s, performed piping design and drafting, put together Bid Packages and installation procedures. Supplied onsite supervision for pre-fabrication and installation.
Project Management and onsite supervision of the building replacement at the Veritti and Chandelier Barges
Provided onsite supervision for numerous maintenance projects in Timbilier Bay field
Hilcorp Energy Corp.
Max Weaver
Project Management for Dredging and Maintenance study and work – Florence Canal. Put together AFE’s and bid Packages
Project Management for 4” Pipeline Installation – Iberia Parish
Project Management for Dredging study and work – Deep Lake
Project Management for Compressor Pad installation – Deep Lake
Provided project management and onsite supervision for the retrieval and re-floating of cargo barges that were pushed on the land by Hurricane Rita
Kerr McGee
Eric Swan
Supervising the E & I Installation on the ST-265-A and ST-265-B Facilities.
LEED Petroleum
Don Disher
Provided onsite personnel for the installation of the Armor Plate composite pipe repair system. The repairs consisted of corrosion abatements on oil process piping and repairs on corroded drain lines.
LL&E
Eldon Fankhauser
Provided onsite supervising for the fabrication of several production packages for ST-229
Provided the management and supervision for the subsea pipeline and facilities installation at GB-236
Provided the management and supervision for the installation of VR-395, EI-371, ST-229 & EI-110 facilities.
Marathon Oil Company
Rick Allred
Provided the onsite inspection services for the fabrication of the 6 throw 2600 HP compressor for EI-349 A.
John Furgeson
Provided the inspection services for the fabrication of the high pressure skids for Vr-369 A and Vr-386 B facilities.
Brian Lasseinge
Provided the onsite inspection services for the fabrication of two 2100 HP compressors for Vr-369 A and Vr-386 B facilities. Provided Inspection services for the fabrication of 23 ASME Coded vessels
Maritech Resources
Monty Richard
Provided onsite supervision for the refurbishment of the WC-630 facility that was damaged by Hurricane Rita.
Provided onsite supervision for the refurbishment of numerous facilities in the West Delta field that were damaged by Hurricane Katrina.
Provided onsite supervision for the refurbishment of numerous facilities in the Eugene Island Field that were damaged by Hurricane Katrina and Rita.
Provided onsite supervision for vessel repairs at EI-305 and SMI-48
Richard Stafford
Provided onsite supervision underwater platform surveys following hurricanes Katrina and Rita.
Wayne Falcon
Provided onsite supervision for the laying of 80,000 feet of infield flowlines for the Timbilier bay field.
Mark Producing
Provided construction inspection for the fabrication and the installation of the WC-300 jacket and deck facilities.
Mobil Exploration & Production
David Dodson
Provided construction management for the fabrication and installation of the EI-119-K Deck and facilities.
Provided construction management for the fabrication and installation of the glob-alt unit on HI-572 facilities. Supervised the completion and installation of the slug catcher of the 12” West Cameron Pipeline.
Supervised and organized the Lowry Gas Plant shutdown to renovate the amine system.
Provided Vender surveillance for the 300 mcf gas to gas exchangers and amine pumps.
Monosep Corporation
Mike Robicheaux
Wrote PowerPoint Presentation for the Produced Water Plan for the Shell’s Pinedale, Wyoming Field
Toby Guidry
Wrote PowerPoint Presentation for reverse osmosis units sales presentation
Ed Godeaux
Provided an in-house Project Manager for the fabrication of a 10M Combosep Unit for SP-62-A. Including documentation, cost management and onsite project supervision.
Provided an in-house Project Manager for the fabrication of a 5M Combosep Unit for SP-62-B. Including documentation, cost management and onsite project supervision.
Provided an in-house Project Manager for the fabrication of a 10M Skimmer Unit for SP-62-C. Including documentation, cost management and onsite project supervision.
Provided an in-house Project Manager for the fabrication of a 30M Flotation Unit for Amerada Hess – Oveng TLP
Provided an in-house Project Manager for the fabrication of a 50M Flotation Unit for Amerada Hess – Okume TLP
Mustang Engineering
Mike Hunt & Paul Redmond
INCO 92 Lake Maracaibo, Venezuela - E & I Inspector / Structural Inspector / Supervisor and inspected the structural fabrication of four 150 ton dehydration modules, one 440 ton common inlet module, and 21 interconnection bridges. Supervised the electrical and Pneumatic installation on the four dehydration modules, one common inlet module and one control module.
Natomas North America
Provided onsite inspection for the fabrication and installation of the living quarters, generator package, production equipment, manifold, flare boom and heliport for WC-72.
Provided Project Management, onsite supervision and inspection services for the hook-up and start-up of the WC-72 facility.
Nerco
Worked as the Supervising Inspector for the decommissioning and removal of two 4-pile platforms and associated pipelines.
Provided inspection for the installation of the jacket and the deck for SS-128
Provided the onsite supervision for the demolition and rebuild of the VR-171 Facilities.
Provided the onsite construction management for the refurbishment, installation and hook-up of the 800 ton deck WC-554.
Provided inspection for the fabrication and installation of a heliport and the deck at SS-201
Occidental Intl - Ecuador
A. D. McReynolds
Provided visual inspection services and onsite supervision for the construction of the central processing facility and well islands.
Petrofac
Joe Haley
Provided onsite supervision and inspection services at Dynamic Industries yard for the production modules for Brazil.
PetroQuest
Bob LeMaire
Project Management for Dredging work – Deep Lake
Jack Block
Provided production operator to review wells and production facilities for optimization of properties in North East Texas
John Steward
Provided project management and onsite supervision for the retrieval and re-floating of cargo barges that were pushed on the land by Hurricane Rita
Sandefer Oil & Gas
Doug Cagle
Provided construction management for various offshore facilities and pipelines.
Seneca Resources
Supervised the removal of the deck and jacket from ST-146-B
Provided onsite supervision for the refurbishment of all the production equipment, the deck and the jacket for EC-149. Provided the onsite inspection services for the installation of EC-149.
Southern Natural Gas
Provided onsite supervision for the installation of the compressor station at Pell City, Al. Supervised the electrical, instrumentation and piping installations.
Superior Oil Company
Jules Abadie
Provided project management and onsite supervision for the Lowry Gas Plant Shutdown and the removal and renovation of the West Cameron slug catcher.
Provided project management and onsite supervision for the installation and erection of all the interconnecting piping and vessels for the Lowry Gas Plant
Provided project management and onsite supervision for the fabrication and installation of the VR-71-1 crude oil platform.
Provided project management and onsite supervision for the fabrication and installation of two offshore compressor packages which included skids, interconnecting piping ASME vessels and instrumentation.
Provided project management and onsite supervision for the fabrication and installation of miscellaneous ASME Code vessels for numerous projects.
United Meridian Corp.
Provided the onsite construction coordination and inspection services for the Tie-in of the 6” pipeline riser for EI-301 B Facilities.
Provided the onsite construction coordination and inspection services for the fabrication of a 4-pile jacket, refurbishment of the deck and the fabrication of a 50’ x 60’ pancake section for WC-524-A Facilities.
Vaalco Energy
Craig Devenney
C-Spect team provided project management and inspection for the
fabrication of the facilities, jackets and decks and install jackets and
decks offshore Gabon.